Delay in home building
There is Delay when construction takes longer than the period agreed upon in your contract. In the Fair Trading Home Building Contract for Work Over $20,000, you will see how long the building process should be.
You can do this by referring to the clauses on:
- Commencement of Work
- Time for Completion
- Extension of Time, and
- Completion of Work
![Fair Trading Contract NSW Commencement of Work Clause](https://www.contractsspecialist.com.au/wp-content/uploads/2022/03/fair-trading-contract-nsw-commencement-of-work-clause-scaled.jpg)
![Fair Trading Contract NSW Time for Completion Clause](https://www.contractsspecialist.com.au/wp-content/uploads/2022/03/fair-trading-contract-nsw-time-for-completion-clause-scaled.jpg)
![Fair Trading Contract NSW Extension of Time Clause](https://www.contractsspecialist.com.au/wp-content/uploads/2022/03/fair-trading-contract-nsw-extension-of-time-clause-scaled.jpg)
![Fair Trading Contract NSW Completion of Work Clause](https://www.contractsspecialist.com.au/wp-content/uploads/2022/03/fair-trading-contract-nsw-completion-of-work-clause-scaled.jpg)
Related Content: Delays and Extensions in Home Building Contracts in NSW
Statutory Warranties
Additionally, the Fair Trading home building contract sets out the Statutory Warranties that require a Builder to finish construction by the date agreed upon, or within a reasonable time. These Statutory Warranties are provided by NSW law (Home Building Act), and parties may not opt out of them.
![Fair Trading Contract NSW Statutory Warranties](https://www.contractsspecialist.com.au/wp-content/uploads/2022/03/fair-trading-contract-nsw-statutory-warranties-scaled.jpg)
When is there Delay?
There is Delay when construction is not completed within the Time for Completion agreed upon in the contract.
When Delay turns to dispute
![Fair Trading Contract NSW Construction Delay](https://www.contractsspecialist.com.au/wp-content/uploads/2022/03/fair-trading-contract-nsw-construction-delay-scaled.jpg)
How to settle dispute from Delay
The first step in resolving any residential construction dispute is to put in genuine effort to talk and come up with a solution that is amenable to both parties. Open, honest communication is key.
If efforts at amicable negotiation fails, recourse may be had under the Fair Trading contracts dispute resolution clause.
This involves sending the Builder a written notice containing the items in dispute. This will be followed by an informal attempt at dispute resolution. If that fails, the parties may undergo mediation, expert appraisal of work, or similar.
![OFT Building Contract Disputes Clause](https://www.contractsspecialist.com.au/wp-content/uploads/2022/02/clause-27-dispute.jpg)
![Fair Trading Home Building Contract Review and Advice NSW](https://www.contractsspecialist.com.au/wp-content/uploads/2022/03/Fair-Trading-Home-Building-Contract-Review-and-Advice-Contracts-Specialist.jpg)
Get Expert Construction Contract Review and Advice
Get Your Fair Trading Contract Reviewed Now
Step 1: Simply fill out this form and upload your contract.
Step 2: We’ll review it and return to you with a fixed fee quote.
Minimise construction risks on cost, time, and quality.
Get Home Building Contract Review and Advice now.
How we can help
At Contracts Specialist, we understand the intricacies of construction delays and the challenges faced by homeowners in NSW. With over a decade of expertise in construction law, I have consistently advised homeowners on their contractual and legal rights. My experience spans advising on Delays associated with the Fair Trading Home Building Contract, clarifying contract rights, assessing risks, and amending contracts to align with homeowners’ intentions. I proudly represent homeowners in NSW, Australia, and all courts of competent jurisdiction, ensuring their interests are always protected.
![Fair Trading Home Building Contract Review Lawyer - John Dela Cruz](https://www.contractsspecialist.com.au/wp-content/uploads/2022/03/Fair-Trading-Home-Building-Contract-Lawyer-John-Dela-Cruz.jpg)
If you’re facing challenges related to construction delays or any other contractual issues, don’t hesitate to reach out. Email us for advice or organise a call with our dedicated construction lawyer. Let’s navigate these complexities together and ensure your rights are safeguarded. Take the first step towards clarity and peace of mind by contacting us today.