The Importance of a Signed Contract
In the Dyjecinska Case, the homeowner, Izabela Dyjecinska, entered into an agreement with the builder, Step Up Renovations (NSW) Pty Ltd. The agreement was a NSW construction contract for alterations and additions. The parties used a Master Builders Association of NSW Residential Building BC4 Contract, commonly known as the MBA BC4 contract.
However, the contract was not signed by either party.
One of the main issues in the dispute was whether the builder could enforce the unsigned contract. The homeowner argued that the unsigned contract meant the builder was in breach of the Home Building Act 1989 (NSW) (Home Building Act) sections 7(1) and 7B. Simply, the Owner’s position was that the contract was unenforceable under section 10(1) of the Home Building Act.
Related content: The Importance of a Signed Contract in Residential Building Projects
Key Findings of the Case
The Appeal Panel allowed the homeowner’s appeal in part, but not with regard to the enforceability of the unsigned contract.
One of the presiding members, Principal Member Thode, held that the plain reading of section 10 of the Home Building Act does not require a signature. Only that the construction contract to be in writing and with sufficiently described works. The Member stated that the provision was intended to prevent builders from enforcing unwritten contracts that were not sufficiently described.
Principal Member Thode held that:
“61. …the omission of a signature from an otherwise standard contract did not create uncertainty of the type requiring specific legislative intervention.”
Additionally, the Principal Member considered it a “capricious argument” for the homeowner to rely on section 10 of the Home Building Act to prevent the builder from enforcing the contract but require the builder to remedy any defect or breach. The Member further expressed:
“This is particularly so in light of the Tribunal’s decision at [122] that “the evidence strongly suggests that [the owner] refused to sign the contract” but permitted the builder to carry out the work.””
This case is distinguished from others on this similar point. A simplified case analysis will help identify the main issues and corresponding ruling.
Key Findings of the Case
Issue | Ruling |
Enforceability of Unsigned Contract | Contract enforceable despite the lack of signature |
Compliance with Act | Contract complied with requirements for being in writing and sufficiently describing works |
The NCAT decision in Dyjecinska distinguished these findings from a recent 2022 NCAT decision of Vujica v TNM Roofing Pty Ltd [2022] NSWCATAP 305. The Principal Member expressed at 59:
For reasons of comity, it is preferable to follow the decisions of the Appeal Panel, but I consider Vujica sufficiently distinguishable from the present case as it did not concern a signed written contract.
Vujica Case vs. Dyjecinska Case - Key Differences
Aspect | Vujica Case | Dyjecinska Case |
Contract Formation | Only a quotation identified as contract | Contract used Master Builders Association of NSW Residential Building BC4 Contract |
Compliance with HB Act s 7(2) | Did not comply; not in writing and insufficient description of work | Complied; contract in writing and sufficiently described works |
Appeal Panel’s Interpretation | ‘Writing’ in s 10 should not be construed narrowly; must meet section 7 requirements | Unsigned contract enforceable as it met section 10 requirements for being in writing and sufficiently describing works |
Implications for Homeowners
The Dyjecinska case highlights the importance of having a signed contract when entering into an agreement with a builder. While the unsigned contract was found enforceable in this instance, it’s crucial to ensure your building contract complies with the requirements of the Home Building Act.
![](https://www.contractsspecialist.com.au/wp-content/uploads/2023/04/Featured-Image-101.jpg)
Conclusion
The recent NCAT case, Dyjecinska v Step-Up Renovations, provides valuable insights for homeowners facing building disputes where a signed contract was not provided. Although the unsigned contract was found enforceable in this case, it is crucial to have a signed contract to avoid potential legal complications.
If you are a homeowner and require advice with a building dispute, then phone our office to speak with a construction lawyer for a 15-minute free consultation.